Learning Centre

What Tenants Should Confirm With Their Landlord Before A Fit-Out

Planning a commercial fit-out in Port Melbourne? Learn what to confirm with your landlord about consent, services, approvals, costs and site rules before work begins.

—
On this page

    Quick Answer

    Pre-Fit-Out Landlord Confirmation

    Before design, procurement or strip-out begins, tenants should obtain written confirmation of landlord consent, responsibility boundaries, base-building conditions, service capacities, approval pathways, site rules, programme dependencies and make-good duties. These checks should inform the proposed commercial fit-out, the division between base-building and tenant works, and any required planning or building approvals.

    Key Takeaways

    • Landlord consent does not replace a planning permit, building permit, health approval, signage consent or other statutory requirement.
    • Lease documents and landlord drawings help define obligations, but they do not prove that physical services have suitable capacity.
    • Record landlord works, tenant works, upgrade costs, access rules, handover records and make-good obligations in a written responsibility matrix.

    Three Tests

    The Three Separate Tests A Commercial Fit-Out May Face

    A proposal may need to pass contractual, landlord and statutory tests. Approval under one test does not automatically satisfy the other two.

    Lease Permission

    The lease or agreement for lease must permit the proposed activity and set out the tenant's rights, responsibilities and restrictions.

    Landlord Acceptance

    The landlord or centre manager may review drawings, contractors, service connections, finishes, signage and construction methods.

    Statutory Approval

    Council, a building surveyor or another authority may need to approve the use, building work, signage or business operation.

    Project Documents

    The lease sets the contractual position, including permitted use, alterations, repair, insurance, access and make-good duties. An agreement for lease may also require landlord works or conditions to be completed before the formal lease starts. Project-specific legal advice may be needed because a builder cannot interpret these documents for you.

    The landlord fit-out guide usually explains submission formats, approved contractors, working hours and building rules. Approved drawings show an accepted design, while written consent records permission and any conditions. None should be treated as interchangeable. Review these documents alongside guidance on base-building responsibilities and construction quote inclusions.

    Verbal support is useful during discussion, but written consent and documented conditions are needed to control construction scope.

    Scope Allocation

    Landlord Or Base-Building Work Versus Tenant Fit-Out Work

    These are common divisions only. The lease, landlord requirements, approved drawings and written scope matrix govern the actual allocation.

    Factor Landlord Or Base Building Tenant Fit-Out
    Structure And Shell May include the primary structure, façade, roof, common areas and tenancy boundary, subject to the lease and delivery condition. May include internal partitions, ceilings, doors, finishes and permitted fixings, with structural changes separately approved.
    Building Services May provide central plant, incoming utilities, fire infrastructure, risers or nominated connection points without guaranteeing spare capacity. Often includes internal distribution, outlets, controls, equipment connections and alterations needed for the tenant's layout and use.
    Upgrades And Approvals Responsibility may apply where agreed landlord works or existing shared infrastructure must be changed, but this cannot be assumed. The tenant may fund use-specific upgrades, consultants and approvals unless the project documents expressly allocate them elsewhere.

    Why A Written Responsibility Matrix Is Worth Preparing

    Practical Benefits

    • Designers and builders can price against clearer boundaries rather than allowing for uncertain landlord or tenant work.
    • Service upgrades, approvals and connection responsibilities can be addressed before procurement commitments are made.
    • The matrix creates a useful record for later design changes, handover questions and make-good discussions.

    Limits To Manage

    • The matrix must remain consistent with the lease and cannot replace project-specific legal advice.
    • Responsibilities may change when site investigation, authority feedback or consultant design reveals additional work.
    • A stated service provision still requires physical verification of its condition, location and available capacity.

    Use And Compliance

    Confirm The Proposed Use And The Complete Approval Path

    Confirm that the lease's permitted use accurately covers the proposed business, not merely a broad commercial description. A tenancy previously used as an office may not automatically suit a clinic, shop or restaurant. The new operation can affect planning permission, building classification, occupant numbers, amenities and ventilation.

    The layout may also affect fire safety, egress, accessible paths, sanitary facilities and essential safety measures. Ask a building surveyor and relevant consultants to identify the likely pathway before design is locked. The distinction between planning and building permits and the purpose of an occupancy permit are important parts of this review.

    A business activity can be acceptable to a landlord yet still require planning, building, health or operational approval.

    Existing Conditions

    Verify The Base Building Rather Than Relying On Leasing Plans

    Request available architectural, structural and services drawings, tenancy delivery schedules, surveys, condition reports and previous approval records. These documents are useful starting points, but they may be diagrammatic, outdated or incomplete. Later alterations and concealed work may not appear on them.

    A site assessment should check dimensions, floor levels, ceiling heights, columns, risers, fire-rated elements, service points and tenancy boundaries. Intrusive investigation needs landlord consent and suitable controls. Ask for any asbestos or hazardous-material information before disturbing older finishes. Guidance on onsite inspections and identifying load-bearing walls explains why visible conditions alone are insufficient.

    Landlord drawings are valuable inputs, but they should not automatically be treated as verified as-built records.

    Documents, Use And Existing-Condition Questions

    Send these questions before the layout and major finishes are finalised.

    • Current Project Documents

      Request the lease, agreement for lease, fit-out guide, tenancy plans, condition report and relevant approval records.

    • Permitted Business Use

      Ask whether the precise activity, operating hours, equipment and expected occupancy are accepted under the tenancy documents.

    • Verified Tenancy Condition

      Confirm access for measurement, surveys, service testing and any approved investigation needed before design or pricing.

    Building Services

    Confirm Service Capacity, Connection Rights And Upgrade Costs

    A service shown on a plan is not necessarily a ready-to-use connection. Confirm the location, condition, metering and available capacity of electricity, data, water, drainage, gas, air conditioning, outside air, exhaust and fire services. Equipment schedules and expected occupancy are needed before consultants can assess demand.

    Hospitality premises may depend on grease management, trade waste and a compliant exhaust route. Offices may require after-hours cooling and data capacity, while professional rooms can need added plumbing and privacy controls. Confirm who approves each connection, who performs the work and who pays for upgrades. See how hospitality fit-outs differ and how base-building responsibilities are commonly divided.

    The existence of a pipe, cable or duct does not confirm that it can support the proposed business operation.

    Services, Structure And Approval Questions

    Record each answer, responsible party, required evidence and date needed for the programme.

    • Capacity And Connection Rights

      Confirm tested service capacity, available connection points, landlord-nominated contractors and metering arrangements.

    • Restricted Building Work

      Ask about slab and wall penetrations, roof access, structural changes, shopfronts, signage and shared-system alterations.

    • Upgrade Cost Allocation

      Identify who funds changes to power, drainage, mechanical, fire, accessibility, amenities and shared infrastructure.

    Design Review

    Understand The Landlord Design Review And Change Process

    Ask what must be submitted at concept, detailed design and construction stages. The landlord may require architectural, structural, mechanical, electrical, hydraulic or fire documentation in nominated formats. It may also require review by its own consultants, with fees or response procedures defined in the project documents.

    Written approval should identify conditions, approved revisions and outstanding matters. Later changes to layouts, equipment, signage or services may require renewed landlord and statutory review. Do not assume that a small visual change has no wider effect. Moving a partition can alter sprinklers, air distribution, lighting, egress and joinery. The process described in moving from empty tenancy to opening day should be read with variation guidance.

    Use revision-controlled drawings so the landlord, consultants and contractor are reviewing the same proposal.

    Site Controls

    Confirm Contractor Access, Work Hours And Building Rules

    Managed and occupied buildings often control inductions, security, working hours, noisy work, dust, odours, loading areas, goods lifts, deliveries, waste removal and common-area protection. Service shutdowns may need advance booking and supervision because they can affect other occupants.

    Ask whether work must occur after hours, whether lifts need protective linings, where materials can be stored and how daily cleaning is handled. These rules influence labour planning, deliveries and trade sequencing, so they should be known before the construction programme is agreed. They are particularly important for office fit-outs and shop fit-outs in shared commercial buildings.

    Straightforward work can become programme-critical when access, shutdowns or noisy tasks are limited to short booking windows.

    Strip-Out Planning

    Set The Demolition And Strip-Out Scope Before Work Begins

    Written landlord approval should identify what can be removed, what must stay and the condition required after strip-out. Confirm retained ceilings, fire-rated elements, shopfronts, services, common walls and landlord-owned equipment. A non-structural-looking partition may conceal live services or form part of an acoustic or fire system.

    Request hazardous-material records and arrange suitable assessment where suspect materials may be disturbed. Service isolation must be verified by authorised people, especially where systems also serve another tenancy. The scope should cover protection, temporary support, waste routes and records of capped or retained services. Review demolition services and guidance on what demolition work can involve before treating strip-out as simple removal.

    Starting strip-out early can expose the tenant to damage, safety and reinstatement risks if the approved removal boundary is unclear.

    Cost And Programme

    Landlord Matters That Can Change Cost Or Timing

    A fit-out budget should reflect the physical tenancy and landlord conditions, not only the visible layout, finishes and floor area.

    1. 01

      Responsibility Gaps

      Unallocated demolition, patching, service connections, approvals or commissioning can emerge as additional tenant scope.

    2. 02

      Access And Upgrades

      After-hours work, shutdown bookings, restricted deliveries and service upgrades can alter labour, sequencing and consultant needs.

    3. 03

      Conditions And Delays

      Latent conditions, review comments, landlord fees, approval changes and make-good duties can affect the wider project budget.

    Access, Cost, Programme And Handover Questions

    These questions connect landlord requirements with pricing, construction sequencing and opening readiness.

    • Access And Site Rules

      Confirm inductions, insurance evidence, credentials, working hours, deliveries, shutdowns, waste and common-area protection.

    • Fees And Security

      Request written details of bonds, deposits, review fees and administration charges without assuming standard amounts.

    • Completion And Make-Good

      List required certificates, as-built records, warranties, keys, defect close-out and end-of-lease reinstatement duties.

    Programme Control

    Identify Possession, Approval And Opening Dependencies

    Confirm the possession date, tenancy handover condition and completion of any landlord works. Design review hold points, permits, service upgrades, shutdown bookings and long-lead equipment should appear in the programme before a construction start or opening target is relied upon.

    Ask what must be complete before contractors enter, whether landlord inspections occur before work is covered, and what documents are needed before trading. Construction completion does not automatically mean the business can open. Utility activation, commissioning, operational licences, occupancy documents, IT and staff setup may remain. The sequence in an empty tenancy to opening day and the distinction around occupancy permission provide useful context.

    Treat the opening date as dependent on approvals, commissioning and operational readiness, not construction alone.

    Lease Exit

    Confirm Handover, Ownership And Make-Good Requirements

    Before construction, establish who will own installed plant, cabling, joinery, signage and service upgrades. Confirm what the landlord expects at project handover, including as-built drawings, certificates, commissioning records, manuals, warranties, approvals, keys and defect close-out evidence.

    Also review the lease-end position. Make-good may require removal of partitions, equipment, signs and cabling, repair of penetrations, reinstatement of finishes or return of services to an agreed arrangement. A fit-out that is difficult to remove can create future exposure. Keep the pre-works condition report, landlord correspondence and approved drawings with the records described in base-building responsibility guidance and construction scope documentation.

    Make-good decisions belong at the start of the lease, when installations can still be designed for removal or agreed retention.

    Common Pre-Fit-Out Mistakes To Avoid

    Most scope problems begin with assumptions that were never physically checked or confirmed in writing.

    Relying on verbal landlord support as final approval

    Do this instead

    Obtain written consent that identifies approved drawings, conditions, responsibility boundaries and any further review stages.

    Treating plans as verified capacity and site information

    Do this instead

    Measure the tenancy and have relevant consultants verify service locations, condition and capacity before design is finalised.

    Starting strip-out before approvals and isolations are complete

    Do this instead

    Approve the removal scope, assess hazardous materials, isolate services and protect retained base-building elements first.

    Practical Example

    How A Suitable-Looking Hospitality Tenancy Can Change

    Consider a Port Melbourne tenancy advertised with power, water and mechanical services. A café concept initially appears workable because the customer area and kitchen fit within the floor plan. Further checks show that drainage is remote from the proposed equipment, slab penetrations are restricted and the existing ventilation system is not a commercial kitchen exhaust route.

    The cooking equipment also increases electrical demand, while new partitions affect sprinklers and the proposed counter narrows accessible circulation. The project now needs revised equipment, layout and services coordination, plus clarification about upgrade costs. This does not mean the tenancy is unsuitable, but it changes feasibility. Compare the issues with hospitality fit-out requirements and hospitality fit-out services.

    A tenancy can contain services without containing the right connections, capacity or landlord permissions for the proposed use.

    Professional Input

    When Specialist Advice Is Worth Obtaining

    Professional input is most useful before the lease position, layout and procurement are locked. A commercial builder can assess buildability, access and construction sequencing. A designer develops the operational layout, while engineers and services consultants assess structure, power, hydraulic, mechanical and fire interfaces.

    A building surveyor confirms the building-permit pathway and performs an independent statutory role. A leasing adviser can explain commercial property matters, while a lawyer can advise on lease clauses, consent and make-good obligations. No single party replaces the others. If the tenancy has uncertain records or complex services, consider an onsite inspection and review when a building permit may be required early.

    Early advice can shape a feasible brief; late advice often arrives after a layout, order or lease commitment is harder to change.

    Our Approach

    How We Approach Commercial Fit-Outs In Port Melbourne

    We approach commercial fit-outs by considering how the proposed operation relates to the existing tenancy, available services, access conditions and approval pathway. Depending on the agreed scope, we can support construction planning from the early stages through to project completion, with consultant input where specialist assessment is required.

    Our experience across retail stores, cafés, beauty salons, medical centres, takeaway premises and boutique commercial spaces helps us recognise practical interfaces between layouts, services and site controls. For projects in Port Melbourne and surrounding suburbs, we focus on clear scope, durable work and efficient construction planning. Explore our shop fit-outs and office fit-outs for related service information.

    Clear landlord answers give the design and construction team a firmer basis for planning, pricing and coordination.

    Have any questions?

    Commercial Fit-Out Landlord FAQs

    Can't find what you're looking for? Feel free to get in touch with our team.

    No. Landlord consent addresses the lease and building-management position, but planning, building, health, signage or other approvals may still apply. Confirm the difference between planning and building permits and check when a building permit is required before regulated work starts.

    The answer depends on the lease, agreement for lease and project-specific responsibility matrix. Do not assume an upgrade is automatically a landlord cost because it affects the base building. Review base-building and tenant responsibilities and ensure the allocation appears in the construction quote scope.

    Only work that is lawfully permitted and authorised should proceed. Early work can create removal, redesign or compliance problems if later approvals change the scope. Check the fit-out path to opening day and clarify occupancy requirements before committing to a staged start.

    Before Proceeding

    What To Confirm Before Design Or Procurement Is Locked

    Before committing to a fit-out, obtain written answers about permitted use, landlord consent, responsibility boundaries, existing conditions, service capacity, structural restrictions, approvals, contractor access, fees, programme hold points, handover and make-good. Record unresolved matters as assumptions rather than allowing them to disappear inside a quotation.

    Confirming these points early does more than complete paperwork. It helps prevent scope being transferred unexpectedly to the tenant and gives designers, consultants and builders a clearer basis for decisions. If you are planning commercial fit-outs in Port Melbourne VIC, review the broader commercial fit-out process or contact our team before the design becomes difficult to change.

    Resolve major uncertainties before final design, ordering and strip-out, when changes are usually easier to manage.

    Keep learning

    Start a Project

    Let's build
    together

    Ready to start your construction project? Get in touch for a free consultation and quote.

    Get Your Free Quote

    Contact

    Get a Free
    Quote

    We'll respond within 24 hours.

    FAQs

    Ask a
    Question

    Can't find what you're looking for? Send us your question and we'll get back to you.